[Mi...] Posted September 22, 2021 Share Posted September 22, 2021 I have a part that is broke into 2 programs from a customer. I want to take both prgs and combine them so as to print everything out on 1 report. Nothing is working for me. I've tried numerous things but come up with nothing. I think I have to use the copy/paste with references?? Or is that used for something totally different?? I could re write the 2nd prg but it has loads of dimensions. Has to be a way to flip it, and use the second prg alignment but im coming up way short ANY help is appreciated Link to comment Share on other sites More sharing options...
[No...] Posted September 22, 2021 Share Posted September 22, 2021 If it suits your needs, you can use copy&paste with references, but you'll have to check if everything has been transferred. I never tried, but somehow I doubt Calypso will copy over nested references. So be sure to check for completeness. You could also include the second program as a macro in the first. That way you could keep the second program unchanged, but it would run as if it was just one. If the alignment of the second program is different from the first, you need to re-create it first and assign it to the macro. Link to comment Share on other sites More sharing options...
[Je...] Posted September 22, 2021 Share Posted September 22, 2021 . . Hi Mike. I've combined programs successfully before. As Norbert mentioned, check carefully that everything transfers correctly. Be especially careful with clearance paths and safety positions. Step the program through slowly until proven and verify the results for plausibility. You can prompt the operator to flip the part by using the programmable stop option in the strategy for a feature. This can be placed inside the strategy for either the last feature before the flip or the first feature after the flip. I've attached a screenshot of this. . . . . Jeff Frodermann, CQI CMM Programmer Meier Tool & Engineering Anoka, Minnesota . . Link to comment Share on other sites More sharing options...
[Mi...] Posted September 22, 2021 Author Share Posted September 22, 2021 Ill give the macro a try. I do not deal with macros much here, but ill giver it a shot and run in slow mo Here goes nothing lol Link to comment Share on other sites More sharing options...
[Cl...] Posted December 30, 2021 Share Posted December 30, 2021 Can anyone explain the procedure for creating a combined program macro? I have two programs, each with a different BA and orientation. I've been ask to combine them using the macro option, if that's even possible? Link to comment Share on other sites More sharing options...
[Me...] Posted December 30, 2021 Share Posted December 30, 2021 I've gone as far as taking a part that laid on the table with two programs for each side and fixtured it to lay sideways on posts. Then combined the two programs into one. Have a star probe on the Eclipse and RDS heads on the two others. Helped with TPs relating two both sides. Link to comment Share on other sites More sharing options...
[Ri...] Posted January 3, 2022 Share Posted January 3, 2022 You want a Master Measurement Plan. Please sign in to view this quote. Please sign in to view this quote. Link to comment Share on other sites More sharing options...
[Er...] Posted January 4, 2022 Share Posted January 4, 2022 bump Link to comment Share on other sites More sharing options...
Recommended Posts