[Ky...] Posted July 16, 2020 Share Posted July 16, 2020 We have parts that we run over and over. My concern is when we save the points for later use if we need them. My concern is if I start at #1 each time will I overwrite the pervious #1's. Am I just worrying about nothing or am I screwing up? Link to comment Share on other sites More sharing options...
[Ch...] Posted July 16, 2020 Share Posted July 16, 2020 I add the date and time(down to the second) to prevent my measuring points files from over writing. Link to comment Share on other sites More sharing options...
[Ow...] Posted July 16, 2020 Share Posted July 16, 2020 Maybe? I always save them with dates like 4.7.20-1. That way if you run them tomorrow they'd be saved as 4.8.20-1 Link to comment Share on other sites More sharing options...
[Ow...] Posted July 16, 2020 Share Posted July 16, 2020 See Link to comment Share on other sites More sharing options...
[Ky...] Posted July 16, 2020 Author Share Posted July 16, 2020 Thanks All for your ideas. We are going to try both and see which idea works for us. I was loading points and saw that I was missing #1 and #2. We have the reports but that just doesn't help sometimes. Next question, how do you handle the program if you add things later on or figure out a better way of running the part after reading something from the Board. Do you obsolete the old program so you don't screw up all the previous point data or what. I have changed somethings in a program then I loaded points and it wanted to rerun some things on a part I didn't have any more. I needed to think about these things years ago. More things to worry about 😮 Thanks for the help and any ideas about the questions above. Kyle Link to comment Share on other sites More sharing options...
[Ke...] Posted July 17, 2020 Share Posted July 17, 2020 As far as making changes to the program you can do several things erase old Characteristics, Mask them, Group them label them something like "Old Characteristics" then mask the whole group. Grouping/keeping them lets you review them later to see your programming progression. Re-Run You can load old points, rename the report and then run "Subsequent Evaluation" then I believe this should keep the original Measuring Points intact. Link to comment Share on other sites More sharing options...
[Ky...] Posted July 17, 2020 Author Share Posted July 17, 2020 Thanks I didn't think about grouping the old and the new. That will make things easier Thanks All Kyle Link to comment Share on other sites More sharing options...