Hello,

I have a project that takes 10:26 min to run photogrammetry and digitalization.

When it finishes it takes 10:23 min to calculate the project.

Polygonization is taking about 8:34 min.

When I open the measurements table most of them are transformed by "Best-fit" and set as "Full resolution".

My question is if "Reference points" method is faster for project calculation over "Best-fit" and if "Full resolution" has some impact too on measurement, calculation or polygonization time.

 

MeasurementsTable.JPG

Link to comment
https://qualityforum.zeiss.com/topic/22380-project-time-reduce/
Share on other sites

Something is off here ...if you are using photog the implication is that you are using reference points.  If nearly all measurements are transformed by best fit indicates something wrong with the setup or some settings issues.

Transformation by best fit is indeed slower from a calculation point of view , varies depending on geometry.